Md Rte 355 Bridge Replacement over CSXT Railroad
Project Overview:
MD355 Bridge over CSXT Railroad In May 2017, Hetzer was awarded a $7.6-million dollar contract to replace an existing bridge on MD355 over CSXT Railroad south of Frederick, MD. The work includes a temporary ACROW truss bridg, centerline sheetpile shoring for support of excavation, H-pile foundations, 430-CY of footing concrete, 535-CY of substructure concrete, a single span steel plate girder bridge, concrete superstructure, significant roadway construction. Significant unforeseen utility relocation delays were mutually resolved by Hetzer and SHA. A late summer 2020 completion is anticipated.
Owner:
Maryland State Highway Administration
District 7 - Frederick County
Facility:
MD355 Bridge over CSXT Railroad
Contract Amount:
$7,569,931
Start to Completion:
July 2017