I-70 / MD 85 Interchange; MD 355 & MD 85 (Phase 2A)

Project Overview:

  • 9,658-CY Compaction Grout for Filling Underground Karst Voids
  • 125,780-BCY Classified Excavation
  • 55,000-BCY Common & Modified Borrow
  • 12,192-LF Highway Storm Drainage Pipe System
  • 112-EA Drainage Structures
  • 2,455-VF 4-FT Diam. Drilled Shafts & 36-inch Diam. Rock Sockets
  • 6,752-SF Erection of Precast Lagging Panels for Retaining Wall
  • 7160-SF Cast-in-Place Concrete Retaining Wall Facing using Form Liner
  • 607-LF Concrete  Traffic Barrier Single Face - Type 1
  • 3,570-LF of Concrete Curb/Gutter & Median Barrier
  • 41,000-SF Concrete Sidewalk
  • 41,370-TN GAB Stone Base Paving & Geosynthetic Stabilized Stone Base
  • 30,290-TN HMA Base & Surface Paving

Owner:

Maryland State Highway Administration

Contract Amount:

$15,242,726

Start to Completion:

July 2002 to October 2005