Maugans Avenue Reconstruction
Project Overview:
- Phased Reconstruction of High Traffic Volume County Road
- 29,160-BCY Total Excavation
- 5,438-LF RCP Storm Drain
- 79-EA Storm Drain Structures
- SWM Facility with 90-CY Concrete Weir Wall
- 12,700-TON GAB Stone Base for Full-Depth Pavement Reconstruction
- 22,600-TON Hot Mix Asphalt Paving Total Tonnage
- 11,977-LF Concrete Curb & Gutter
- 16,395-SF Concrete Sidewalk
- Segmental Modular Block Retaining Walls
- Major Subcontracts included Traffic Signals, Lighting, & Pavement Markings
Owner:
Washington County, Maryland
Division of Public Works
Contract Amount:
$7,927,204
Start to Completion:
March 2007 to April 2009