Maugans Avenue Reconstruction

Project Overview:

  • Phased Reconstruction of High Traffic Volume County Road
  • 29,160-BCY Total Excavation
  • 5,438-LF RCP Storm Drain
  • 79-EA Storm Drain Structures
  • SWM Facility with 90-CY Concrete Weir Wall
  • 12,700-TON GAB Stone Base for Full-Depth Pavement Reconstruction
  • 22,600-TON Hot Mix Asphalt Paving Total Tonnage
  • 11,977-LF Concrete Curb & Gutter
  • 16,395-SF Concrete Sidewalk
  • Segmental Modular Block Retaining Walls
  • Major Subcontracts included Traffic Signals, Lighting, & Pavement Markings

Owner:

Washington County, Maryland

Division of Public Works

Contract Amount:

$7,927,204

Start to Completion:

March 2007 to April 2009