JDB Locust Grove & JDB Hirst Farm Multiple Phase Site Development
Project Overview:
- 108.0 Acre Site Development
- Full site development services, including:
- Bulk excavation & grading
- Major Storm Water Management Facilities
- Closed Storm Drain Collection System
- 7-VF to 34-VF Deep Sanitary Interceptor Sewer
- Domestic Water & Sanitary Sewer Utilities
- Concrete Curb & Gutter, Sidewalk, & Driveway Aprons
- HMA Paving
Contract Amount:
$9,272,710
Start to Completion:
January 2002 to December 2006