JDB Locust Grove & JDB Hirst Farm Multiple Phase Site Development

Project Overview:

  • 108.0 Acre Site Development
  • Full site development services, including:
    • Bulk excavation & grading
    • Major Storm Water Management Facilities
    • Closed Storm Drain Collection System
    • 7-VF to 34-VF Deep Sanitary Interceptor Sewer 
    • Domestic Water & Sanitary Sewer Utilities
    • Concrete Curb & Gutter, Sidewalk, & Driveway Aprons
    • HMA Paving

Contract Amount:

$9,272,710

Start to Completion:

January 2002 to December 2006