FedEx Hagerstown Hub Project

Project Overview:

  • 2-EA Storm Water Management Facilities
  • 1,022,830-BCY Total Bulk Excavation
  • 11,184-LF Storm Drain Piping
  • 15,041-LF Domestic & Fire Protection Water Line
  • 6,906-LF Sanitary Sewer Piping
  • 2-EA Sanitary Sewer Pump Stations
  • 93,580-TN Stone Base Paving
  • 65,270-TN HMA Base & Surface Paving

Facility:

FedEx Ground Package System, Inc.

Contract Amount:

$14,199,000

Start to Completion:

September 2003 to February 2006