New Interconnection Water Main & Storage Tank Replacement
Project Overview:
- Water Storage Tank Demolition & Replacement
- Construct Water Boosting Pump Station
- 1,900-LF 10-inch PVC Push-Joint Waterline
- 9,850-LF 12-inch PVC Push-Joint Waterline
- 6-EA Fire Hydrants
- 14-EA 12-inch MJ Gate Valves
Owner:
City of Charles Town, WV
Contract Amount:
$1,934,205
Start to Completion:
September 2006 to August 2007