Miscellaneous HMA Paving
Project Overview:
Total HMA Plant Production To-Date Thru 2019 Season: 4,087,289-TONS
HMA Plant Description:
- Astec M – Pack Drum Plant – 270 ton/hour, with 4 storage silos (3 with a capacity of 150 tons and 1 with a capacity of 200 tons). Storage silo cones are hot oil jacketed. New Inner/Outer shell replacement installed in January 2018. Two each TAV-35D 35,000 gallon Heatec Thermo-Guard vertical liquid asphalt storage tanks installed in January 2019.
- Physical location: 10104 Mapleville Road, Hagerstown, MD 21740
Notable Single Project HMA Tonnages:
- 100,200-TONS: Interstate 81 / Halfway Blvd. Interchange Reconstruction & I-81 Resurfacing from Halfway Blvd. to Pennsylvania State Line
- 59,735-TONS: Target Distribution Center, Chambersburg, PA
- 65,270-TONS: FedEx Ground Package System, Inc., Hagerstown, Maryland Hub Project
- 47,653-TONS: FedEx Freight BTS Facility, Hagerstown, Maryland
- 52,515-TONS: 2002 Washington County Overlay
- 33,600-TONS: 2002 Frederick Airport - Runway 5-23 Rehab & Taxiway A Ext Rehab
- 30,290-TONS: MdSHA I-70/MD 85 Interchange - MD 355 & MD 85 (Phase 2A)
- 48,120-TONS: 2005 WACO Pavement Maintenance Program
- 29,750-TONS: 2006 Frederick County, MD - Full Depth Pavement Reclamation
- 43,250-TONS: 2007 MdSHA Washington County Mill & Resurface
- 37,170-TONS: 2008 WACO Pavement Maintenance Program
- 46,550-TONS: 2009 FedEx Freight BTS Facility
- 33,150-TONS: 2009 WACO Pavement Maintenance Program
- 36,770-TONS: 2009-2010 MdSHA State Maintenance for Washington County
- 31,430-TONS: 2010 Frederick County, MD - Reich's Ford Road Reconstruction
- 29,090-TONS: 2010 WACO Pavement Maintenance Program
- 36,280-TONS: 2011-2012 MdSHA State Maintenance for Frederick County
- 31,060-TONS: 2012-2015: MdSHA I-70 @ MD 63 Bridges Replacement
- 47,980-TONS: 2014: WACO Pavement Maintenance Program
- 24,642-TONS: 2015-2016: MdSHA I-81 NB (Halfway Blvd to PA State Line)
- 167,495-TONS: 2016-2020: WA344 I-81 Potomac River Bridge Paving Subcontract