Lake Holiday Bridge over Concrete Spillway
Project Overview:
Features:
- Concrete Spillway Demolition & Replacement for a 240-AC Impoundment
- Construct New 127-FT 2-span Bridge, including Prestressed Concrete Bulb-Tee Beams
- Lower and Maintain Lake Elevation to Permit Construction with 3-EA 18” Siphons
- Temporary Relocation of Underground Utilities
- Excavate Spillway Into Existing Bed Rock Subgrade
- Permanent Underground Utilities Relocation
- Roadway Reconstruction
- Approximately 7,050-CY of Concrete Construction, including:
- Bridge Construction 504-CY
- Spillway Slabs & Footings 3,467-CY
- Training Walls & Baffle Blocks 1,203-CY
- Spillway Labrynth Walls 639-CY
- Curved Approach Retaining Walls 215-CY
- Other (Fill & Edge) Concrete 1,022-CY
Owner:
Frederick County, Virginia – Department of Public Works, Lake Holiday Sanitary District
Facility:
Lake Holiday Dam Spillway Upgrade, Concrete Spillway Reconstruction
Contract Amount:
$7,105,260
Start to Completion:
September 2011 to June 2013