Frederick Airport Runway 5-23 Rehabilitation & Taxiway A Extension
Project Overview:
- 170,000-BCY Bulk Excavation
- 86,900-SY Pavement Milling
- 16,000-TONS Stone Base Paving
- 31,675-TONS HMA Paving
- 60-ACRES Turf Establishment
- Major Subcontract - Airfield Lighting Subcontract, featuring:
- New taxiway edge, runway edge, and threshold lighting
- New PAPI System
- New REIL System
- New Localizer System
Facility:
City of Frederick, Maryland - Municipal Airport
Contract Amount:
$4,854,953
Start to Completion:
May 2003 to August 2004