2016 Frdrk Cnty, VA - CDD Landfill Cap

Project Overview:

  • Develop 4-AC Adjacent Borrow Site.
  • Excavate & Screen 45,000-BCY of borrow material.
  • Trench & lay 3,500-LF 6" HDPE gas venting system piping.
  • Place 13,000-BCY 6" Bedding Soil.
  • Subcontract Furnish & Placement of LLDPE Liner - 10.2-Acres.
  • Place 28,000-BCY of 18" Cover Soil.
  • Trench & lay combined 7,500-LF of 8" to 12" diameter HDPE downchutes, Cap Drains, & Toe Trench Drains.
  • Maintain & repair 1,800-SY existing roadway. 
  • Screen & place 9,000-CY of 6" Topsoil.
  • Trench & lay combined 1,500-LF of 24" & 30" RCP storm drain system.

Owner:

Fredrerick County, VA

Department of Public Works

Facility:

Fredrerick County, VA Regional Landfill

Contract Amount:

$2,151,000.00

Start to Completion:

April 2016 to October 2016